Project Details
Land Number
C167
Region
Al Nargis District, 5th settlement
HOMEi Price
14,500.00 EGP
Neighbour Price
23,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 25% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
155 m²
Delivery
Unit Delivery Date
December 2025
Average Unit Price
2,011,500 EGP
Project Location
Map View
Al Nargis District, 5th settlement
HOMEi Timeline
License office contract
October 5, 2023
Submitting the license
October 10, 2023
Receiving the license
October 30, 2023
Excavation permit
November 1, 2023
Mining permit
November 2, 2023
Construction contract in progress
November 10, 2023
Construction contract signed
November 15, 2023
Excavation
December 11, 2023
Plain concrete
December 23, 2023
Reinforced concrete
January 4, 2024
Reinforced foundations
January 16, 2024
Footings insulation
January 27, 2024
Backfilling over footings
January 28, 2024
Basement columns
February 9, 2024
Basement walls
February 21, 2024
External plaster for basement
March 4, 2024
Basement slab
March 16, 2024
Ground floor columns
March 28, 2024
Ground floor walls
April 9, 2024
Ground floor slab
April 21, 2024
First floor columns
May 3, 2024
First floor walls
May 15, 2024
First floor slab
May 27, 2024
Second floor columns
June 8, 2024
Second floor walls
June 20, 2024
Second floor slab
July 2, 2024
Submitting third-floor extension license
July 4, 2024
Third floor columns
July 27, 2024
Third floor walls
August 8, 2024
Third floor slab
August 20, 2024
Roof extension license
September 1, 2024
Roof concrete works
September 4, 2024
Roof walls
September 19, 2024
External fence
November 23, 2024
Finishing works
January 22, 2025
Elevator
February 11, 2025
Project handover to the authority
December 23, 2025
Utilities meter installation
December 25, 2025