Project Details
Land Number
479
Region
October Gardens series, 6th October
HOMEi Price
6,700.00 EGP
Neighbour Price
15,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
| 2 |
|
- | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 25% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
155 m²
Delivery
Unit Delivery Date
July 2024
Average Unit Price
938,250 EGP
Project Location
Map View
October Gardens series, 6th October
HOMEi Timeline
License office contract
August 2, 2023
Submitting the license
August 7, 2023
Receiving the license
August 22, 2023
Excavation permit
August 23, 2023
Mining permit
August 24, 2023
Construction contract in progress
September 5, 2023
Construction contract signed
September 10, 2023
Excavation
September 26, 2023
Plain concrete
October 1, 2023
Reinforced concrete
October 6, 2023
Footings insulation
October 21, 2023
Backfilling over footings
October 26, 2023
Basement columns
October 27, 2023
Basement walls
October 31, 2023
Basement slab
November 10, 2023
Ground floor columns
November 20, 2023
Ground floor walls
November 30, 2023
Ground floor slab
December 10, 2023
First floor columns
December 20, 2023
First floor walls
December 30, 2023
First floor slab
January 9, 2024
Second floor columns
January 19, 2024
Second floor walls
January 29, 2024
Second floor slab
February 8, 2024
Submitting third-floor extension license
February 10, 2024
Third floor columns
March 4, 2024
Third floor walls
March 14, 2024
Third floor slab
March 24, 2024
Roof extension license
March 25, 2024
Roof concrete works
April 8, 2024
Roof walls
April 23, 2024
External fence
June 7, 2024
External plaster for basement
July 7, 2024
Finishing works
July 7, 2024
Elevator
July 22, 2024