Project Details
Land Number
1158
Region
The Area 22, El Sadat City
HOMEi Price
7,500.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 15% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
| 5 | During Construction | 5% |
| 6 | During Construction | 5% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
195 m²
Delivery
Unit Delivery Date
December 2026
Average Unit Price
1,090,125 EGP
Project Location
Map View
The Area 22, El Sadat City
HOMEi Timeline
License office contract
March 25, 2025
Submitting the license
April 1, 2025
Receiving the license
May 1, 2025
Excavation permit
June 1, 2025
Mining permit
June 3, 2025
Construction contract in progress
June 15, 2025
Construction contract signed
June 20, 2025
Excavation
July 4, 2025
Plain foundations
July 10, 2025
Reinforced foundations
July 19, 2025
Footings insulation
July 31, 2025
Backfilling around foundations
August 2, 2025
Basement columns
August 3, 2025
Basement slab
November 16, 2025
Ground floor columns
November 23, 2025
Ground floor slab
November 30, 2025
First floor columns
December 9, 2025
First floor slab
October 28, 2025
Second floor columns
November 7, 2025
Second floor slab
November 22, 2025
Submitting third-floor extension license
November 23, 2025
Receiving third-floor extension license
February 20, 2026
Third floor columns
February 27, 2026
Fence columns
March 14, 2026
Wall Building works
March 15, 2026
Third floor slab
March 20, 2026
Roof extension license
June 18, 2026
Roof room columns
June 28, 2026
Roof room slab
July 19, 2026
Basement walls
July 29, 2026
Ground floor walls
August 8, 2026
First floor walls
August 9, 2026
Second floor walls
August 19, 2026
Third floor walls
August 29, 2026
Roof walls
September 8, 2026
Wooden door frames
September 22, 2026
Plumbing main works
September 23, 2026
Electrical final finishes
October 3, 2026
Electrical finishing
November 20, 2026
Plumbing finishing
November 21, 2026
Plaster and putty
November 22, 2026
Marble works
December 1, 2026
Aluminum & glass works (Krital)
December 2, 2026
Elevator
December 27, 2026