Project Details
Land Number
1327
Region
The Area 29, El Sadat City
HOMEi Price
4,500.00 EGP
Neighbour Price
10,000.00 EGP
Construction Companies
| # | Company | Title | Status |
|---|---|---|---|
| 1 |
|
Construction | Finished |
| 2 |
|
- | Finished |
| 3 |
|
- | Finished |
Payment Plan
| Instalment Number | Duration | Percentage Paid |
|---|---|---|
| 1 | On Booking | 50% |
| 2 | During Construction | 25% |
| 3 | During Construction | 15% |
| 4 | During Construction | 10% |
Unit Details
Bedrooms
3
Bathrooms
2
Area
175 m²
Delivery
Unit Delivery Date
September 2025
Average Unit Price
634,500 EGP
Project Location
Map View
The Area 29, El Sadat City
HOMEi Timeline
License office contract
November 10, 2023
Building permit
November 15, 2023
Excavation permit
November 25, 2023
Mining permit
November 26, 2023
Extracting a Building water meter
November 29, 2023
Obtaining a construction insurance certificate
November 29, 2023
Construction contract in progress
December 1, 2023
Construction contract signed
December 1, 2023
Excavation
December 5, 2023
Plain concrete
December 7, 2023
Reinforced concrete
December 7, 2023
Footings insulation
December 11, 2023
Backfilling around foundations
December 11, 2023
Basement columns
December 20, 2023
Basement slab
December 30, 2023
Ground floor columns
January 1, 2024
Ground floor slab
January 22, 2024
Basement walls
January 26, 2024
First floor columns
February 8, 2024
First floor slab
February 28, 2024
Second floor columns
March 9, 2024
Second floor slab
August 24, 2024
Third-floor addition permit
September 14, 2024
Obtaining an insurance certificate for a third-floor extension
November 15, 2024
Third floor columns
December 14, 2024
Third floor slab
December 24, 2024
Roof extension license
January 14, 2025
Obtaining a roof insurance certificate
January 14, 2025
Roof concrete works
April 4, 2025
Ground floor walls
April 28, 2025
First floor walls
May 8, 2025
Second floor walls
May 18, 2025
Third floor walls
May 28, 2025
Roof walls
June 8, 2025
Concrete works for the external wall
June 15, 2025
Wall Building works
July 6, 2025
Wooden door frames
July 6, 2025
Electrical works
July 7, 2025
Plumbing works
July 8, 2025
Plaster and putty
July 11, 2025
Marble works
August 20, 2025
Aluminum & glass works (Krital)
August 20, 2025
Elevator
August 25, 2025
Project handover to the authority
August 30, 2025
Utilities meter installation
September 1, 2025